150 Charles Street
1938 warehouse, adapted 2015, 91 residences across 16 floors.
150 Charles Street, 10014
150 Charles Street is the former Whitehall Storage warehouse of 1938, adapted and reclad by COOKFOX and completed in 2015. The warehouse was concrete, brick and glass, and it was kept rather than cleared, so the building standing now is the old frame carrying a new envelope.
The structural grid of the warehouse survives and sets the plan. Each bay of that grid defines one townhouse along Charles Street and West 10th Street, which is why ten of the residences have their own doors to the street rather than a route through the lobby. Working in one of those means the party walls are the original concrete frame, and the bay is the unit of the plan whether or not the layout wants it to be.
A concrete frame fixes window positions and gives deep reveals. The openings land where the frame allows, and the reveal depth is a real dimension, deep enough to detail into for blinds, shutters or a seat rather than something to be papered over.
Above the streetwall the building steps back in stacked volumes, and the setbacks carry planted terraces. Anything built on those terraces is sharing its space with soil and irrigation, so the loading and the drainage are settled before the joinery is.
Keeping the frame cost the plan its freedom and bought the street its scale. On a block of nineteenth century houses that is the trade worth making, and it is legible from the sidewalk in a way a replacement building would not have been.
Within walking distance
Building facts
Built
1938
Last altered
2011
Floors
16
Residences
91
New York City Primary Land Use Tax Lot Output, version 26v1. Tax lot 1006367503.
Public records show 150 CHARLES STREET was built in 1938 and rises 16 floors with 91 residential units (NYC MapPLUTO, version 26v2). This building is an individual landmark, designated Jun 16, 1997 by the Landmarks Preservation Commission (NYC Open Data). This lot falls within the No, designated Jun 16, 1997 by the Landmarks Preservation Commission (NYC Open Data). The Department of Buildings has 50 or more job filings on record for this lot (NYC Open Data).
Public record
Last altered
1988
Total units
92
Landmark
Historic Street Lampposts
Historic district
No
Total permits
50 or more
NYC MapPLUTO 26v2, NYC Open Data. Tax lot 1006367503. Violations and permits as of October 28, 2026.
43 filings in the last 24 months, 1 open violation, last filing Apr 2026
The record
Permits and violations from the Department of Buildings and the Housing Preservation and Development, newest first.
DOB NOW filings from June 2016.
INSTALL REPLACEMENT CHIMNEY AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Filed estimated cost: $275,000 (as filed, not verified)
4TH FLOOR - RELOCATE RESIDENTIAL WASHER, REMOVE SINK, REPLACE DRAIN IN SHOWER AREA
Filed estimated cost: $22,000 (as filed, not verified)
Removal of Spilt System Condenser on roof, new toilet and dryer exhaust ductwork being installed on floors 14, 15, and 16, and installation of new condensers on 15th floor and Roof. No change in use, egress, or occupancy.
Filed estimated cost: $100,000 (as filed, not verified)
Application being filed for the interior alteration of an existing 1-family dwelling unit on the 16th floor. No change of use, egress or occupancy.
Filed estimated cost: $180,150 (as filed, not verified)
4TH FLR - CONVERT SHOWER IN BATHROOM FOR WASHER/DRYER. NEW GLASS & METAL PARTITION BTWN DINING & NEW STUDY. CLAD WALL W/WD PANELING. PROVIDE NEW DOOR FROM STUDY TO UTILITY ROOM. 5TH FLR - INSTALL DECORATIVE BEAMS IN PRIMARY BDRM, CLAD WALLS IN BDRM.
Filed estimated cost: $476,567 (as filed, not verified)
Application being filed for the reframing of existing bulkhead and new concrete pad at the 16th floor as per plans filed herewith. No change in use, egress, or occupancy.
Filed estimated cost: $35,000 (as filed, not verified)
Installation of an outdoor grill and piping to Hot Tub on the 16th floor as per plans filed herewith. No change in use, egress, or occupancy.
Filed estimated cost: $10,000 (as filed, not verified)
Application being filed for the reframing of existing bulkhead and new concrete pad at the 16th floor as per plans filed herewith. No change in use, egress, or occupancy.
Filed estimated cost: $35,000 (as filed, not verified)
RENOVATION OF EXISTING RESIDENTIAL APARTMENT W/ NEW PLUMBING FIXTURES IN KITCHEN & BATHROOMS TO INCLUDE NEW PIPING & VALVES. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Filed estimated cost: $74,000 (as filed, not verified)
RENOVATION OF EXISTING RESIDENTIAL SPACE, RELOCATION & ADDITION OF NEW SPRINKLERS. NEW SPRINKLERS SHALL BE PROVIDED AS PER NFPA 13 & NYS BUILDING CODE
Filed estimated cost: $15,000 (as filed, not verified)
INTERIOR RENOVATION OF UNIT M6. MINOR DEMOLITION IN CELLAR, FIRST & SECOND FLOOR AS PER PLANS. NEW INTERIOR PARTITIONS & DOORS, FINISHES, PLUMBING & LIGHTING AS PER PLANS. NEW RAILINGS & STAIR REPAIRS.NO CHANGE IN EGRESS, USE OR OCCUPANCY
Filed estimated cost: $100,000 (as filed, not verified)
INTERIOR RENOVATION OF UNIT M6. MINOR DEMOLITION IN CELLAR, FIRST & SECOND FLOOR AS PER PLANS. NEW INTERIOR PARTITIONS & DOORS, FINISHES, PLUMBING & LIGHTING AS PER PLANS. NEW RAILINGS & STAIR REPAIRS.NO CHANGE IN EGRESS, USE OR OCCUPANCY
Filed estimated cost: $100,000 (as filed, not verified)
Proposed: plumbing and sprinkler work associated with the interior renovation of the existing triplex level apartments ( 14th-16th floors). No change of use, egress or occupancy.
Filed estimated cost: $237,200 (as filed, not verified)
RECONFIGURE EXISTING DUCTWORK RUNS AND INSTALL 2 NEW DIFFUSERS. RE-LOCATE THERMOSTATS.
Filed estimated cost: $15,000 (as filed, not verified)
RECONFIGURE EXISTING DUCTWORK RUNS AND INSTALL 2 NEW DIFFUSERS. RE-LOCATE THERMOSTATS.
Filed estimated cost: $15,000 (as filed, not verified)
Proposed: plumbing and sprinkler work associated with the interior renovation of the existing triplex level apartments ( 14th-16th floors). No change of use, egress or occupancy.
Filed estimated cost: $237,200 (as filed, not verified)
PROPOSED: REMOVAL OF EXISTING AC UNITS, DUCTWORK, DIFFUSERS, FANS, AND RELATED MECHANICAL PIPING IN COUNJUNCTION WITH THE GENERAL RENOVATION WORK. NO CHANGE OF USE, EGRESS OR OCCUPANCY
Filed estimated cost: $100,000 (as filed, not verified)
PROPOSED: REMOVAL OF EXISTING AC UNITS, DUCTWORK, DIFFUSERS, FANS, AND RELATED MECHANICAL PIPING IN COUNJUNCTION WITH THE GENERAL RENOVATION WORK. NO CHANGE OF USE, EGRESS OR OCCUPANCY
Filed estimated cost: $100,000 (as filed, not verified)
PROPOSED: REMOVAL OF EXISTING AC UNITS, DUCTWORK, DIFFUSERS, FANS, AND RELATED MECHANICAL PIPING IN COUNJUNCTION WITH THE GENERAL RENOVATION WORK. NO CHANGE OF USE, EGRESS OR OCCUPANCY
Filed estimated cost: $100,000 (as filed, not verified)
PROPOSED: REMOVAL OF EXISTING AC UNITS, DUCTWORK, DIFFUSERS, FANS, AND RELATED MECHANICAL PIPING IN COUNJUNCTION WITH THE GENERAL RENOVATION WORK. NO CHANGE OF USE, EGRESS OR OCCUPANCY
Filed estimated cost: $100,000 (as filed, not verified)
Proposed: demolition and removal of all interior fit out down to sub-surfaces for apartment PHB ( 14th -16th floors). No enlargement proposed and party walls and fire walls to remain in their entirety). No change of use, egress or occupancy.
Filed estimated cost: $474,000 (as filed, not verified)
Proposed: demolition and removal of all interior fit out down to sub-surfaces for apartment PHB ( 14th -16th floors). No enlargement proposed and party walls and fire walls to remain in their entirety). No change of use, egress or occupancy.
Filed estimated cost: $474,000 (as filed, not verified)
Proposed: demolition and removal of all interior fit out down to sub-surfaces for apartment PHB ( 14th -16th floors). No enlargement proposed and party walls and fire walls to remain in their entirety). No change of use, egress or occupancy.
Filed estimated cost: $474,000 (as filed, not verified)
Proposed: demolition and removal of all interior fit out down to sub-surfaces for apartment PHB ( 14th -16th floors). No enlargement proposed and party walls and fire walls to remain in their entirety). No change of use, egress or occupancy.
Filed estimated cost: $474,000 (as filed, not verified)
Proposed: structural alteration of the existing PHB# level apartments ( 14th -16th floor).
Filed estimated cost: $75,000 (as filed, not verified)
Proposed: structural alteration of the existing PHB# level apartments ( 14th -16th floor).
Filed estimated cost: $75,000 (as filed, not verified)
Proposed: structural alteration of the existing PHB# level apartments ( 14th -16th floor).
Filed estimated cost: $75,000 (as filed, not verified)
Proposed: structural alteration of the existing PHB# level apartments ( 14th -16th floor).
Filed estimated cost: $75,000 (as filed, not verified)
IRA to assist with Condition Assessment
Filed estimated cost: 0 (as filed, not verified)
PLUMBING WORK FILED IN CONJUNCTION WITH RENOVATION TO EXISTING APT. 7BS. INSTALL PLUMBING FIXTURES AND RELATED PIPING.
Filed estimated cost: $66,590 (as filed, not verified)
MECHANICAL WORK FILED ON CONJUNCTION WITH RENOVATION TO EX. APT. 7BS. INSTALL NEW FAN COIL UNITS, ASSOCIATED DUCTWORK AND DIFFUSERS. INSTALL TOILET EXHAUST.
Filed estimated cost: $81,510 (as filed, not verified)
PLUMBING WORK FILED IN CONJUNCTION WITH RENOVATION TO EXISTING APT. 7BS. INSTALL PLUMBING FIXTURES AND RELATED PIPING.
Filed estimated cost: $66,590 (as filed, not verified)
MECHANICAL WORK FILED ON CONJUNCTION WITH RENOVATION TO EX. APT. 7BS. INSTALL NEW FAN COIL UNITS, ASSOCIATED DUCTWORK AND DIFFUSERS. INSTALL TOILET EXHAUST.
Filed estimated cost: $81,510 (as filed, not verified)
SPRINKLER WORK FILED IN CONJUNCTION WITH RENOVATION TO EXISTING APT. 7BS. MODIFY EXISTING SPRINKLER SYSTEM FOR NEW APT LAYOUT. INSTALL SPRINKLER HEADS AND RELATED SPRINKLER PIPING.
Filed estimated cost: $102,600 (as filed, not verified)
INTERIOR RENOVATION OF EX. APT. 7BS. DEMOLISH AND CONSTRUCT NON-STRUCTURAL WALLS, DOORS, FLOORING AND FINISHES. NO CHANGES TO USE, EGRESS OR OCCUPANCY.
Filed estimated cost: $337,500 (as filed, not verified)
INTERIOR RENOVATION OF EX. APT. 7BS. DEMOLISH AND CONSTRUCT NON-STRUCTURAL WALLS, DOORS, FLOORING AND FINISHES. NO CHANGES TO USE, EGRESS OR OCCUPANCY.
Filed estimated cost: $337,500 (as filed, not verified)
Structural work for new opening for stair through ninth floor slab for combination of Unit 9C & 8BN.
Filed estimated cost: $19,989 (as filed, not verified)
Structural work for new opening for stair through ninth floor slab for combination of Unit 9C & 8BN.
Filed estimated cost: $19,989 (as filed, not verified)
Sprinkler work to combine Unit 9C & 8BN
Filed estimated cost: $29,975 (as filed, not verified)
Mechanical work to combine Unit 9C & 8BN
Filed estimated cost: $149,986 (as filed, not verified)
General construction to combine Unit 9C & 8BN. Combine dwelling units per DOB Technical Policy Procedure Notice # 3/1997
Filed estimated cost: $6,603,399 (as filed, not verified)
Plumbing work to combine Unit 9C & 8BN.
Filed estimated cost: $89,974 (as filed, not verified)
Plumbing work to combine Unit 9C & 8BN.
Filed estimated cost: $89,974 (as filed, not verified)
5 earlier filings, 2024
Mechanical work to combine Unit 9C & 8BN
Filed estimated cost: $149,986 (as filed, not verified)
General construction to combine Unit 9C & 8BN. Combine dwelling units per DOB Technical Policy Procedure Notice # 3/1997
Filed estimated cost: $6,603,399 (as filed, not verified)
Plumbing work to combine Unit 9C & 8BN.
Filed estimated cost: $89,974 (as filed, not verified)
Plumbing work to combine Unit 9C & 8BN.
Filed estimated cost: $89,974 (as filed, not verified)
PROPOSED INTERIOR MODIFICATIONS ON 4TH FLOOR UNIT 4DS AS SHOWN ON PLANS
Filed estimated cost: $72,100 (as filed, not verified)
1 resolved
§27-2107 ADM CODE OWNER FAILED TO FILE A VALID REGISTRATION STATEMENT WITH THE DEPARTMENT AS REQUIRED BY ADM CODE §27-2097 AND IS THEREFORE SUBJECT TO CIVIL PENALTIES, PROHIBITED FROM CERTIFYING VIOLATIONS, AND DENIED THE RIGHT TO RECOVER POSSESSION OF PREMISES FOR NONPAYMENT OF RENT UNTIL A VALID REGISTRATION STATEMENT IS FILED.
Source: NYC Department of Buildings and Housing Preservation and Development violations, via NYC Open Data.
Condo documents are recorded at unit level. Search a unit to see them.
Pre-2016 DOB filings
DOB legacy · NYC Open Data
DOB Job Application Filings (ic3t-wcy2), NYC Open Data. As of October 28, 2026.
DOB legacy violations
DOB BIS · NYC Open Data
FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022
49 resolved, most recent Sep 22, 2022
FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
CONFIRMED SUBMISSION. · disposed Sep 22, 2022
FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
ECB DISMISSED · disposed May 19, 2022
PPN203 AOC SUB 11/29/2021 BY OTIS ELEVATOR COMPCERT 434061 GUDESHWAR PERSAUD · disposed Dec 5, 2021
PPN203 AOC SUB 11/29/2021 BY OTIS ELEVATOR COMPCERT 434061 GUDESHWAR PERSAUD · disposed Dec 5, 2021
PPN203 AOC SUB 11/29/2021 BY OTIS ELEVATOR COMPCERT 434061 GUDESHWAR PERSAUD · disposed Dec 5, 2021
PPN203 AOC SUB 11/29/2021 BY OTIS ELEVATOR COMPCERT 434061 GUDESHWAR PERSAUD · disposed Dec 5, 2021
PPN203 AOC SUB 11/29/2021 BY OTIS ELEVATOR COMPCERT 434061 GUDESHWAR PERSAUD · disposed Dec 5, 2021
PPN203 AOC SUB ON 11/4/20 BY OTIS ELEVATOR CERT# 055716 GUDESHWAR PERSAUD · disposed Nov 16, 2020
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
CAT 1 2017 AOC, PAID LATE FEES · disposed Sep 12, 2019
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
CAT 1 2017 AOC, PAID LATE FEE · disposed Sep 12, 2019
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
CAT 1 2017 AOC PAID LATE FEE · disposed Sep 12, 2019
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
CAT 1 2017 AOC, PAID LATE FEE · disposed Sep 12, 2019
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
CAT 1 2017 AOC, PAID LATE FEE · disposed Sep 12, 2019
PPN203 AOC SUB ON 8/7/19 BY:OTIS ELEV. CO. G. LUBERA, CERT#056129 · disposed Aug 22, 2019
PPN203 AOC SUB ON 8/7/19 BY:OTIS ELEV. CO. G. LUBERA, CERT#056129 · disposed Aug 22, 2019
PPN203 AOC SUB ON 8/7/19 BY:OTIS ELEV. CO. G. LUBERA, CERT#056129 · disposed Aug 22, 2019
PPN203 AOC SUB ON 8/7/19 BY:OTIS ELEV. CO. G. LUBERA, CERT#056129 · disposed Aug 22, 2019
PPN203 AOC SUB ON 8/7/19 BY:OTIS ELEV. CO. G. LUBERA, CERT#056129 · disposed Aug 22, 2019
PPN203 AOC SUB ON 8/7/19 BY:OTIS ELEV. CO. G. LUBERA, CERT#056129 · disposed Aug 22, 2019
VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
EVCAT1 2017 CAT1 TEST DONE ON 9/15/17 · disposed Oct 21, 2019
VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
EVCAT1 2017 CAT1 TEST DONE ON 9/15/17 · disposed Oct 21, 2019
VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
EVCAT1 2017 CAT1 TEST DONE ON 9/15/17 · disposed Oct 21, 2019
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
CAT1 2016 AOC LATE FILING,PENALTY FEE PAID. · disposed May 1, 2018
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
CAT1 2016 AOC LATE FILING,PENALTY FEE PAID. · disposed May 1, 2018
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
CAT1 2016 AOC LATE FILING,PENALTY FEE PAID. · disposed May 1, 2018
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
CAT1 2016 AOC LATE FILING,PENALTY FEE PAID. · disposed May 1, 2018
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
CAT1 2016 AOC LATE FILING,PENALTY FEE PAID. · disposed May 1, 2018
PPN203 AOC SUB 011918 BY OTIS ELEVATOR CERT 56107 G.LUBERA · disposed Feb 4, 2018
PPN203 AOC SUB ON 09/07/17 BY:OTIS ELEVATOR CO.WILLIAM CAHILL, CERT#56117 · disposed Sep 20, 2017
PPN203 AOC SUB ON 09/07/17 BY:OTIS ELEVATOR CO.WILLIAM CAHILL, CERT#56117 · disposed Sep 20, 2017
PPN203 AOC SUB ON 09/07/17 BY:OTIS ELEVATOR CO.WILLIAM CAHILL, CERT#56117 · disposed Sep 20, 2017
PPN203 AOC SUB ON 09/07/17 BY:OTIS ELEVATOR CO.WILLIAM CAHILL, CERT#56117 · disposed Sep 20, 2017
PPN203 AOC SUB ON 12/11/17 BY:OTIS ELEVATOR CHARLES NOAH, CERT#56161 · disposed Jan 16, 2018
VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2015 INSPECTION/TEST
CAT 1 EA#1220/14 SO/04/05/2016#2657 · disposed Jun 14, 2018
VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2015 INSPECTION/TEST
CAT 1 EA#232/15 SO/050916#2527 · disposed Jun 14, 2018
FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
PD INV#61799233 · disposed Feb 12, 2017
FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
PD INV#61799257 · disposed Feb 12, 2017
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2014 INSPECTION REPORT
RASCIA CANCELLED-OP-49 SUB BL#82431-01 REMOVED AS OF 3/10/11 · disposed Feb 18, 2016
VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2014 INSPECTION/TEST
EVCAT1 NEW INSTALLATION/EA920/13-FI/051215 · disposed Jul 9, 2015
VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2014 INSPECTION/TEST
EVCAT1 NEW INSTALLATION/EA921/13-FI/031415 · disposed Jul 9, 2015
VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2014 INSPECTION/TEST
EVCAT1 NEW INSTALLATION/EA911/13-FI/051215 · disposed Jul 9, 2015
VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2014 INSPECTION/TEST
EVCAT1 NEW INSTALLATION/EA904/13-FI/031415 · disposed Jul 9, 2015
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT
RASCIA CANCELLED-OP-49 SUB BL#82431-01 REMOVED AS OF 3/10/11 · disposed Feb 18, 2016
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT
CIAKKG CANCEL, DEVICE INSTALLED IN 2014 · disposed May 31, 2015
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT
CIAKKG CANCEL, DEVICE INSTALLED IN 2014 · disposed May 31, 2015
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT
CIAKKG CANCEL, DEVICE INSTALLED IN 2014 · disposed May 31, 2015
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT
CIAKKG CANCEL, DEVICE INSTALLED IN 2014 · disposed May 31, 2015
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT
RASCIA CANCELLED-OP-49 SUB BL#82431-01 REMOVED AS OF 3/10/11 · disposed Feb 18, 2016
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2011 INSPECTION REPORT
RASCIA CANCELLED-OP-49 SUB BL#82431-01 REMOVED AS OF 3/10/11 · disposed Feb 18, 2016
DOB BIS Violations (3h2n-5cm9), NYC Open Data. As of October 28, 2026.
ECB violations
Environmental Control Board · NYC Open Data
40 resolved, most recent Nov 25, 2021
FAILURE TO NOTIFY THE DOB PRIOR TO COMMENCEMENT OF WORK THAT REQUIRES TPP. AT TIME OF INSPECTION OBSERVED WORK BEING JUNE IN APT 8AN UNDER THE AFOREMENTION JOB#. 72HRS NOTIFICATION IS REQUIRED TO BE PROVIDED TO
Penalty: $1,250 · paid: $1,250
28-201.1 INADEQUATE TENANT PROTECTION PLAN.AT TIME OF INSPECTION OBSERVED WORK BEING PERFORMED UNDER THE AFOREMENTIONED JOB NUMBER.THE SUBMITTED TPPP LACKS SPECIFIC MEANS AND METHODS ON HOW TO PROTECT TENANTS A
WORK WITHOUT ELECTRICAL PERMIT. NOTE: DURING TIME OF INSPECTION, OBSERVED ELECTRICAL WORK PERFORMED IN APARTMENT 6BS ON THE 6TH FLOOR, ELECTRICAL OUTLETS AND NEW ELECTRICAL PANELS ADDED WITH NO PERMIT FILED FO
Penalty: $800 · paid: $800
FAILURE TO SAFEGUARD ALL PERSONS & PROPERTY AFFECTED BY CONSTRUCTION OPRATIONS. AT TIME OF INSPECTION OBSERVED ACTIVE JOB SITE. THE SITE SAFETY MANAGER STATED THAT A WORKER ON THE 15TH FL WAS INDURED WHEN A
Penalty: $1,200 · paid: $1,200
OPER OF CRANE W/AND EXP CD.@ TIME OF INSP CD #4461 CD HAD EXP ON 03/29/14.CD HAS TO BE VALID WHILE ON-SITE ON A JOB SITE.REMEDY:OBTAIN CD/RENEW.
Penalty: $2,430 · paid: $2,430
WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS/OR APPROVED AMENDMENTS. NOTICED AT TIME OF INSPECTION AT EXP4 ADJACENT BLDG MISSINGROOF PROTECTION SITE SAFETY PLAN SHOWS 20FT PROTECTION FOR ADJACENT
Penalty: $2,400 · paid: $2,400
FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING. NOTICED AT TIME OF INSPECTION AT EXP 1 LOADING DOCK SNOW & ICE DEBR. NOT REMOVED. WORKERS WORKINGUNLOADING TRUCKS. WORKERS ALSO USING AS A MEANS OOOF INEGRESS & EGRESS
Penalty: $2,400 · paid: $2,400
NO CONCRETE SAFETY MANAGER PRESENT DURING ALL CONCRETE OPERATIONS AS REQUIRED. NOTICED AT TIME OF INSPECTION WORKERS FRAMING CONCRETE FORMS FOR WALLS ON OUTSIDE EXP2 AT 14TH FL NO CONCRETE SAFETY MANAGER ON
FAILURE TO NOTIFY THE DOB W/IN 24 TO 48 HOURS OF THE START OF EXCAVATION. AT THE TIME OF INSPECTION, EXCAVATION FOR NEW BUILDING WAS COMPLETED AND THE DOB WAS NOT NOTIFIED OF THE START OF EXCAVATION.RMDY:OFFICI
WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND APPROVED AMENDMENTS.DRAWING SHOWED 4'X16' STEEL IBEAM ON BUILDING SIDE.THEY USED 4'X20'X12"TIMBER MATT.NO AMENDMENTS & NOT APPROVED.RMDY:CONFORM TO
Penalty: $2,500 · paid: $557
3301.5 INSP OF EQUIP- UNABLE TO PRODUCE INSPECTION/MAINTENANCE LOGS ATTIME OF INSP.AT TIME OF INSPECTION MR.BRIAN MOORE NYDL#838914258 (D) WAS OPERATING A CRANE & DID NOT HAVE ANY DAILY OR MONTHLY INSP LOGS TO
Penalty: $400 · paid: $400
FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTIONOPERATIONS.AT TIME OF INSPECTION MR.BRIAN MOORE NYDL#838914258(D)WAS OPERATING A CRANE W/O ANY DUNNAGE/IMPROPER DUNNAGE.REM:USE PROPER DUNNA
OPERATION OF CRANE W/O CERTIFICATE OF ONSITE INSPECTION.AT TIME OF INSPECTION MR.BRIAN MOORE NYDL#838914258(D)WAS OPERATING A CRANE AT A NEWBLDG,ERECTING STEEL AND DID NOT HAVE ANY APPROVED PLANS(NO CN)REM:OBTA
Penalty: $2,400 · paid: $2,400
OPERATION OF CRANE W/O CERTIFICATE OF APPROVAL/OPERATION,NO CD.AT TIMEOF INSPECTION MR.BAIAN MOORE NY DL#838914258(D)WAS OPERATING A CRANE W/O AND CD.CRANE WAS 6600LBS AND HAS 50'BOOM CAPACITY.REM:OBTAIN CD.
Penalty: $2,400 · paid: $2,400
INADEQUATE SAFETY MEASURES OPERATION OF CRANE/HOISTING EQUIP IN A UNSAFE MANNER.AT TIME OF INSPECTION MR.BRIAN MOORE NY.DL#838914258(D)WAS OPERATING A CRANE THAT DID NOT HAVE NO/IMPROPER DUNNAGE WHILE LIFTING A
Penalty: $4,800 · paid: $4,800
WORK W/O A PERMIT. AT THE TIME OF AN AUDIT INSPECTION, SPYDER CRANE, SN #29C5011 WAS BEING USED, SET-UP ON THE 9TH FLR TO MOVE MATERIALS FROM OTHER FLRS BELOW. NO EQUIPMENT USE PERMIT ALONG W/ APPROVED
Penalty: $1,630 · paid: $1,630
BC3307.4 WARNING SIGN&LIGHTS TO PROTECT PUBLIC FROM HAZARDS.DANGER FLASHING BEACON MISSING FROM TOP OF PLASTIC BARRICADES ON 10TH ST WHERE LANE IS OCCUPIED BY CONTRACTOR FOR CONCRETE PUMP TRUCK.RMDY:PROVIDE FLA
BC3301.2 FAILURE TO SAFEGUARD ALL PERSONAL PROPERTY AFFECTED BY CONSTRUCTION OPERATION NOTE AT TIME OF INSPECTION WORK IN PROGRESS FORM WORKERECTING SLAB OF CELLAR OBSERVED THROUGHOUT SITE REBAR CAPS MISSING VA
Penalty: $1,600 · paid: $1,600
SEC. 28-105.12.8. WORK IS NOT IN ACCORDANCE W/SITE SAFETY PLAN. THE DIRECTION OF THE CONSTRUCTION RAMP WAS CHANGED DURING THE FOUNDATION & EXCAVATION PHASE OF THE PROJECT AS A RESULT OF THIS NON-CONFORMANCE
Penalty: $1,600 · paid: $1,600
FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTIONOPERATIONS. AT EXP 1 THE BACK END OF THE RAMP IS MISSING FULL GUARDRAILS IN AREAS WHERE THE RAMP IS GREATER THAN 5'. REBAR CAPS ARE MISSING
Penalty: $2,400 · paid: $2,400
28.105.12.8.WORK IS NOT IN ACCORDANCE WITH SITE SAFETY PLAN.AT TIME OFINSPECTION I DID OBSERVE @EXPOSURE #3 "WEST 10TH STREET SIDE" THE VERTICAL RAMP TO HAVE AN INCLINE OF APPROX 1:2 INSTEAD OF THE REQUIRED 1:4
SEC. 3304.7 SAFE MEANS OF INGRESS & EGRESS IN ADEQUATE AT TIME OF INSPECTION. UPON INSPECTION OBSERVED EXCAVATION IN PROGRESS W/O (2) DEFINEEGRESS AT LEAST 25'-0" (APART) EITHER BY LADDER AT RAMP AS REQUIRED BY
FFAILURE TO SAFE GUARD ALL PERSON & PROPERTY AFFECTED BY CONSTRUCTION OPERATION. NO GUARD RAILS AT TIME INSPECTION BUILDING UNDER ALT PERMIT#104869509. A SECTION OF GUARD RAILS MISSING ALONG NORTH ELEVATION
Penalty: $1,200 · paid: $1,200
FAILURE TO SAFEGUARD ALL PERSONS & PROPERTY AFFECTED BY CONSTRUCTION OPERATIONS.PARTIAL STOP WORK ORDER ISSUED PURSUANT TO 28-207.2 & POSTED @ PREMISES-@ TIME OF INSPECTION OBSERVED WATER MAIN BREAK CAUSED BY M
Penalty: $2,400 · paid: $2,400
FAILURE TO PROVIDE ADEQUATE PROTECTION FOR SIDEWALK & WALKWAYS DURING CONSTR. OPERATIONS NOTED:AT FRONT OF PREMISES FROM 1ST FL TO ROOF LEVEL PERFORMED BRICK RE-POINTING BRICK JOINTS RAKE-OUT WITH NO PROTECTION
Penalty: $5,000 · paid: $3,273
CU:5M7/44M7/58J1/55Y13/51U7/3M7/.5M-PROVIDE MISSING CAR GATE.44M-GOVERNOR SEAL MISSING RECALIBRATOR & PROPERLY SEAL.51U-PROVIDE HOIST ROPE TAG.3M-PROVIDE SIGN FOR FREIGHT USE ONLY.
Penalty: $800 · paid: $800
86BB5,19M007,85M05,1M7,02M07. 86-2 YR TEST 85-5 YR TEST 19-WORN.
Penalty: $2,500 · paid: $2,500
86U05/47U05/66O02/28Q07/60T7/41M07 #41-M-07 WRONG DEVICE NO ON ID TAG # 41-M-07 PROVIDE PROPER CITY ID NO.
57O02/ 74O02/ 35P07/ 74-O-02 CLEAN CAR TOP 35-P-07 PROVIDE ALLESS TO OTOR REAR
Penalty: $180 · paid: $180
INSTALLATION OF MECHANICAL EQUIPMENT WITHOUT 1ST OBTAINING AN EQUIP- MENT USE PERMIT. NOTED: 3 YORK A/C UNITS LOCATED ON ROOF. MODEL #S H2CE120A2SC; H4CE090A2SA; H1CE180A2SD. NO EQUIP USE PERMITS AVAILABLE
Penalty: $2,500
FAILURE TO MAINTAIN EXTERIOR BUILDING WALL. DEFECT IS: AT NORTH WALL ON CHARLES ST AND SOUTH WALL ON WEST 10 ST, CHANKS OF CONCRETE MISSINGLOOSE, SEPARATING AND IN DANGER OF FALLING FROM 2ND THRU ROOF CREATING
Penalty: $800 · paid: $800
73U15I 73-PERFORM 3 YEAR TEST AND TAG 15-REPAIR HATCH DOOR EACH MECHANISM.
74-74-PROVIDE ACCESS TO BUILDING (REFUSED)
ALTERED BUILDING OCCUPIED WITHOUT A VALID CERTIFICATE OF OCCUPANCY UNDER OPEN ALT. 304/89 4TH FLOOR OFFICE. REMEDY: OBTAIN VALID C OF O
Penalty: $350 · paid: $350
11Q,53B,73U.
11Q,53B,73U.
ALTERED BUILDING OCCUPIED WITHOUT A VALID CERTIFICATE OF OCCUPANCY UNDER ALT. 304-89. LOCATION 4 FLOOR OFFICE. REMEDY: OBTAIN A NEW CERTIFICATE OF OCCUPANCY
Penalty: $500 · paid: $607
ALTERED BUILDING OCCUPIED WITHOUT A VALID CERTIFICATE OF OCCUPANCY UNDER 304-89 LOCATION 4TH FLOOR OFFICE. REMEDY: OBTAIN A NEW CERTIFICATE OF OCCUPANCY
Penalty: $350 · paid: $350
ALTERED BUILDING OCCUPIED WITHOUT A VALID C OF O UNDER OPEN ALTERATION 304/89 LOCATION 4 FL OFFICE REMEDY OBTAIN A VALID C OF O
Penalty: $250 · paid: $250
ALTERED BUILDING OCCUPIED WITHOUT A VALID C OF O UNDER OPENALT 304/89 AT 4 FL OFFICE REMEYD OBTAIN A VLAID C OF O
Penalty: $285 · paid: $285
ECB Violations (6bgk-3dad), NYC Open Data. As of October 28, 2026.
Certificates of occupancy
DOB · NYC Open Data
19 earlier certificates
DOB NOW CofO (pkdm-hqz6) and DOB Legacy CofO (bs8b-p36w), NYC Open Data. As of October 28, 2026.
What are you trying to do here?
Public records for 150 CHARLES STREET, Manhattan. Data from NYC Open Data: NYC MapPLUTO, Department of Buildings (DOB NOW, BIS, ECB), Housing Preservation and Development, Landmarks Preservation Commission, ACRIS (NYC Department of Finance), DOF Digital Tax Map. Address lookup by NYC Planning Labs Geosearch. Page updated October 28, 2026.