← Buildings

515 Park Avenue

Built in 1998, a 43 floor limestone tower on Park Avenue.

515 Park Avenue, 10022

515 Park Ave

515 Park Avenue was designed by Frank Williams and Associates and completed in 1998, a forty three storey tower of limestone, cast stone and beige brick.

It was drawn deliberately in the manner of the pre-war Park and Fifth Avenue houses, and the borrowing is structural rather than decorative. The plans are large, the windows are punched rather than continuous, and the ceilings are high, reaching around eleven and a half feet in the penthouse.

That makes it behave more like its pre-war neighbours than like the glass towers of its own decade. There is solid wall between openings, so storage and millwork can sit against an outside wall, and the acoustic and thermal work is not thrown onto soft furnishings alone.

The difference from a genuine pre-war building is that the structure is modern. Cross walls are not all masonry and the services were laid out in 1998 rather than adapted from 1926, so there is more freedom to move a partition than the appearance suggests.

Within walking distance

244 mChristofle · store
269 mFantini · showroom
269 mGaggenau · showroom
284 mBeauvais Carpets · showroom
324 mSamuel & Sons · showroom
347 mClaremont Furnishings · showroom

Building facts

Built

1998

Floors

43

Residences

57

New York City Primary Land Use Tax Lot Output, version 26v1. Tax lot 1013947501.

Public records show 515 PARK AVENUE was built in 1998 and rises 42 floors with 57 residential units (NYC MapPLUTO, version 26v2). No HPD violations are recorded for this lot (NYC Open Data, as of October 27, 2026). The Department of Buildings has 32 job filings on record for this lot (NYC Open Data).

Public record

Total units

96

Total permits

32

NYC MapPLUTO 26v2, NYC Open Data. Tax lot 1013947501. Violations and permits as of October 27, 2026.

24 filings in the last 24 months, 16 open violations, last filing May 2026

The record

Permits and violations from the Department of Buildings and the Housing Preservation and Development, newest first.

DOB NOW filings from June 2016.

Suspended ScaffoldFiled by CENTRAL CONSTRUCTION MGMTlic. 006591Permit Issued · May 21, 2026 · job M01394012-I1

INSTALLATION OF INDUSTRIAL ROPE ACCESS FOR FACADE INSPECTIONS.

Filed estimated cost: 0 (as filed, not verified)

Mechanical SystemsFiled by HITE CONSTRUCTION INClic. 026230Permit Issued · Mar 2, 2026 · job M01251915-S2

Modification of existing mechanical system. Work to include new AC Unit, fan coils, & related ductwork; and toilet and kitchen exhaust, as per plans filed herewith. No change in use, egress or occupancy.

Filed estimated cost: $88,000 (as filed, not verified)

StructuralFiled by HITE CONSTRUCTION INClic. 026230Permit Issued · Jan 19, 2026 · job M01251915-S3

Replace existing convenience stair & related framing in apt. #15/16 as per plans filed herewith. No change in use, egress, or occupancy.

Filed estimated cost: $45,000 (as filed, not verified)

General ConstructionFiled by HITE CONSTRUCTION INClic. 026230Permit Issued · Sep 14, 2025 · job M01251915-I1

Interior renovation of existing duplex apartment #15/16 (floors 14 and 15) . Work to include non-structural demolition and finishes. No change in use, egress, or occupancy.

Filed estimated cost: $618,860 (as filed, not verified)

PlumbingFiled by DONATO PLUMBING, INClic. 002426Permit Issued · Sep 14, 2025 · job M01251915-S1

Modification to plumbing system to duplex apartment #15/16 (Floors 14 and 15 )per plans filed herewith. No change to use, egress, or occupancy.

Filed estimated cost: $96,000 (as filed, not verified)

General ConstructionFiled by HITE CONSTRUCTION INClic. 026230Permit Issued · Sep 14, 2025 · job M01251915-I1

Interior renovation of existing duplex apartment #15/16 (floors 14 and 15) . Work to include non-structural demolition and finishes. No change in use, egress, or occupancy.

Filed estimated cost: $618,860 (as filed, not verified)

PlumbingFiled by DONATO PLUMBING, INClic. 002426Permit Issued · Sep 14, 2025 · job M01251915-S1

Modification to plumbing system to duplex apartment #15/16 (Floors 14 and 15 )per plans filed herewith. No change to use, egress, or occupancy.

Filed estimated cost: $96,000 (as filed, not verified)

Mechanical SystemsFiled by HIGHLINE CONSTRUCTION GRlic. 610210Permit Issued · Jul 1, 2025 · job M01212334-I1

Filing herewith mechanical work for an existing duplex, work includes new fan coil units (FCU) and kitchen, toilet and laundry exhaust systems. No change to use, occupancy or egress.

Filed estimated cost: $575,000 (as filed, not verified)

Mechanical SystemsFiled by HIGHLINE CONSTRUCTION GRlic. 610210Permit Issued · Jul 1, 2025 · job M01212334-I1

Filing herewith mechanical work for an existing duplex, work includes new fan coil units (FCU) and kitchen, toilet and laundry exhaust systems. No change to use, occupancy or egress.

Filed estimated cost: $575,000 (as filed, not verified)

Mechanical SystemsFiled by HIGHLINE CONSTRUCTION GRlic. 610210Permit Issued · Jul 1, 2025 · job M01212334-I1

Filing herewith mechanical work for an existing duplex, work includes new fan coil units (FCU) and kitchen, toilet and laundry exhaust systems. No change to use, occupancy or egress.

Filed estimated cost: $575,000 (as filed, not verified)

StructuralFiled by HIGHLINE CONSTRUCTION GRlic. 610210Signed-off · Jun 30, 2025 · job M01212356-I1

Infill of existing stair opening proposed and create new stair opening for an existing duplex. No change of use, occupancy or egress.

Filed estimated cost: $85,000 (as filed, not verified)

StructuralFiled by HIGHLINE CONSTRUCTION GRlic. 610210Signed-off · Jun 30, 2025 · job M01212356-I1

Infill of existing stair opening proposed and create new stair opening for an existing duplex. No change of use, occupancy or egress.

Filed estimated cost: $85,000 (as filed, not verified)

PlumbingFiled by DONATO PLUMBING, INClic. 002426Permit Issued · Jun 23, 2025 · job M01212316-I1

Plumbing work proposed for an existing duplex. No change of use, occupancy or egress.

Filed estimated cost: $117,000 (as filed, not verified)

PlumbingFiled by DONATO PLUMBING, INClic. 002426Permit Issued · Jun 23, 2025 · job M01212316-I1

Plumbing work proposed for an existing duplex. No change of use, occupancy or egress.

Filed estimated cost: $117,000 (as filed, not verified)

General ConstructionFiled by HIGHLINE CONSTRUCTION GRlic. 610210Permit Issued · Jun 22, 2025 · job M01212391-I1

Interior renovation of an existing duplex. No change to use, occupancy or egress.

Filed estimated cost: $2,500,000 (as filed, not verified)

General ConstructionFiled by HIGHLINE CONSTRUCTION GRlic. 610210Permit Issued · Jun 22, 2025 · job M01212391-I1

Interior renovation of an existing duplex. No change to use, occupancy or egress.

Filed estimated cost: $2,500,000 (as filed, not verified)

General ConstructionFiled by HIGHLINE CONSTRUCTION GRlic. 610210Permit Issued · Jun 22, 2025 · job M01212391-I1

Interior renovation of an existing duplex. No change to use, occupancy or egress.

Filed estimated cost: $2,500,000 (as filed, not verified)

Mechanical SystemsFiled by C.N. RENOVATION CO., INClic. 002999Signed-off · Sep 23, 2024 · job M01067849-S2

Mechanical work filed in conjunction with apartment renovation on the 12th Floor.

Filed estimated cost: $249,925 (as filed, not verified)

Mechanical SystemsFiled by C.N. RENOVATION CO., INClic. 002999Signed-off · Sep 23, 2024 · job M01067849-S2

Mechanical work filed in conjunction with apartment renovation on the 12th Floor.

Filed estimated cost: $249,925 (as filed, not verified)

Mechanical SystemsFiled by MATCO SERVICE CORPlic. 008662Signed-off · Sep 9, 2024 · job M01095675-I1

Modification/additions to existing HVAC system and related ductwork/piping as per plans filed herewith. No change in use, egress or occupancy under this application.

Filed estimated cost: $800,000 (as filed, not verified)

PlumbingFiled by ARCON PLBG SOLUTIONSlic. 002424Signed-off · Aug 25, 2024 · job M01067849-S1

Plumbing work filed in conjunction with apartment renovation on the 12th Floor.

Filed estimated cost: $124,000 (as filed, not verified)

PlumbingFiled by ARCON PLBG SOLUTIONSlic. 002424Signed-off · Aug 25, 2024 · job M01067849-S1

Plumbing work filed in conjunction with apartment renovation on the 12th Floor.

Filed estimated cost: $124,000 (as filed, not verified)

General ConstructionFiled by C.N. RENOVATION CO., INClic. 002999Signed-off · Aug 18, 2024 · job M01067849-I1

Renovation of an existing apartment on the 12th Floor. Work include non-structural demolition and general construction as per plans filed herewith.

Filed estimated cost: $783,450 (as filed, not verified)

General ConstructionFiled by C.N. RENOVATION CO., INClic. 002999Signed-off · Aug 18, 2024 · job M01067849-I1

Renovation of an existing apartment on the 12th Floor. Work include non-structural demolition and general construction as per plans filed herewith.

Filed estimated cost: $783,450 (as filed, not verified)

8 earlier filings, 2023–2024
Mechanical SystemsFiled by REMODELING SPACE NY LLClic. 612050Signed-off · Feb 21, 2023 · job M00801692-I1

Mechanical work at existing class A apartment. No change of use, egress or occupancy under this application.

Filed estimated cost: $250,000 (as filed, not verified)

Mechanical SystemsFiled by REMODELING SPACE NY LLClic. 612050Signed-off · Feb 21, 2023 · job M00801692-I1

Mechanical work at existing class A apartment. No change of use, egress or occupancy under this application.

Filed estimated cost: $250,000 (as filed, not verified)

Mechanical SystemsFiled by REMODELING SPACE NY LLClic. 612050Signed-off · Feb 21, 2023 · job M00801692-I1

Mechanical work at existing class A apartment. No change of use, egress or occupancy under this application.

Filed estimated cost: $250,000 (as filed, not verified)

PlumbingFiled by A.M.N. CORPORATIONlic. 001884Signed-off · Feb 5, 2023 · job M08048162-I1

Installation of plumbing fixtures at 38th and 39th floors in conjunction with interior renovation. No change of use, egress or occupancy under this application.

Filed estimated cost: $200,000 (as filed, not verified)

PlumbingFiled by A.M.N. CORPORATIONlic. 001884Signed-off · Feb 5, 2023 · job M08048162-I1

Installation of plumbing fixtures at 38th and 39th floors in conjunction with interior renovation. No change of use, egress or occupancy under this application.

Filed estimated cost: $200,000 (as filed, not verified)

General ConstructionFiled by REMODELING SPACE NY LLClic. 612050Permit Issued · Jan 11, 2023 · job M08048157-I1

Interior renovation of existing class A apartment at 38th & 39th floors. No change of use, egress or occupancy under this application.

Filed estimated cost: $500,000 (as filed, not verified)

General ConstructionFiled by REMODELING SPACE NY LLClic. 612050Permit Issued · Jan 11, 2023 · job M08048157-I1

Interior renovation of existing class A apartment at 38th & 39th floors. No change of use, egress or occupancy under this application.

Filed estimated cost: $500,000 (as filed, not verified)

General ConstructionFiled by REMODELING SPACE NY LLClic. 612050Permit Issued · Jan 11, 2023 · job M08048157-I1

Interior renovation of existing class A apartment at 38th & 39th floors. No change of use, egress or occupancy under this application.

Filed estimated cost: $500,000 (as filed, not verified)

Source: NYC Department of Buildings and Housing Preservation and Development violations, via NYC Open Data.

Condo documents are recorded at unit level. Search a unit to see them.

HPD maintenance complaints

HPD · NYC Open Data

HEATING — HEAT RELATEDCLOSE · Aug 16, 2003

More than one complaint was received for this building-wide condition. This complaint status is for the initial complaint.The Department of Housing Preservation and Development contacted a tenant in the building and verified that the following conditions were corrected. The complaint has been closed. If the condition still exists, please file a new complaint.

HEATING — HEAT RELATEDCLOSE · Aug 16, 2003

The Department of Housing Preservation and Development responded to a complaint of no heat or hot water and was advised by a tenant in the building that heat and hot water had been restored. If the condition still exists, please file a new complaint.

HPD Maintenance Code Complaints (ygpa-z7cr), NYC Open Data. As of October 27, 2026.

Pre-2016 DOB filings

DOB legacy · NYC Open Data

38 A2 filings1997–2019
12 A3 filings1990–2013

DOB Job Application Filings (ic3t-wcy2), NYC Open Data. As of October 27, 2026.

DOB legacy violations

DOB BIS · NYC Open Data

E-ELEVATOR ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEDec 20, 2021
E-ELEVATOR ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEDec 20, 2021
E-ELEVATOR ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEDec 20, 2021
E-ELEVATOR ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEDec 20, 2021
ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVESep 5, 2019

VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST

ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVESep 5, 2019

VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST

ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVESep 5, 2019

VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST

EVCAT5-NON-RESIDENTIAL ELEVATOR PERIODIC INSPECTION/TEST ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEMay 19, 2019

FAILURE TO PERFORM CATEGORY 5 INSPECTION

EVCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEApr 4, 2019

VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST

E-ELEVATOR ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEAug 2, 2018
EVCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEOct 30, 2014

VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2013 INSPECTION/TEST

ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEMay 29, 2014

VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST

EVCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVESep 30, 2012

VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2011 INSPECTION/TEST

EVCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEDec 12, 2011

VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2010 INSPECTION/TEST

VCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED — V-DOB VIOLATION - ACTIVEOct 7, 2010
35 resolved, most recent Oct 7, 2024
EGRADE-FAILURE TO POST ENERGY GRADE/SCORE NONE — V*-DOB VIOLATION - DISMISSEDNov 30, 2023

FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3

CIANOW CRM Violation Dismissed · disposed Oct 7, 2024

EGRADE-FAILURE TO POST ENERGY GRADE/SCORE NONE — V*-DOB VIOLATION - DISMISSEDNov 30, 2022

FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3

CIANOW CRM Violation Dismissed · disposed Oct 7, 2024

EGRADE-FAILURE TO POST ENERGY GRADE/SCORE NONE — V*-DOB VIOLATION - DISMISSEDNov 30, 2021

FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3

CIANOW CRM Violation Dismissed · disposed Oct 7, 2024

EGRADE-FAILURE TO POST ENERGY GRADE/SCORE NONE — V*-DOB VIOLATION - DISMISSEDApr 28, 2021

FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3

CIANOW CRM Violation Dismissed · disposed Oct 7, 2024

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 2, 2018

PPN203 AOC SUB 012722 BY OTIS ELEV CO GUDESHWAR PERSAUD CERT#434061 · disposed Feb 2, 2022

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 2, 2018

PPN203 AOC SUB 012722 BY OTIS ELEV CO GUDESHWAR PERSAUD CERT#434061 · disposed Feb 2, 2022

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 2, 2018

PPN203 AOC SUB 012722 BY OTIS ELEV CO GUDESHWAR PERSAUD CERT#434061 · disposed Feb 2, 2022

ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED — V*-DOB VIOLATION - DISMISSEDJan 2, 2017

VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST

JMA 2015 AOC PERFORMED 1-9-16 PENALTY PAID INV#61798781 · disposed Mar 2, 2017

ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED — V*-DOB VIOLATION - DISMISSEDJan 2, 2017

VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST

JMA 2015 AOC PERFORMED 1-9-16 PENALTY PAID INV#61798780 · disposed Mar 2, 2017

ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED — V*-DOB VIOLATION - DISMISSEDJan 2, 2017

VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST

JMA 2015 AOC PERFORMED 1-9-16 PENALTY PAID INV#61798779 · disposed Mar 2, 2017

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJul 10, 2016

PVT: RESOLVED BY SATISFACTORY CAT 1 INSPECTION · disposed Apr 6, 2017

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJul 10, 2016

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jan 5, 2017

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJul 10, 2016

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jan 5, 2017

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJul 10, 2016

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jan 5, 2017

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 10, 2015

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jul 26, 2016

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 10, 2015

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jan 5, 2017

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 17, 2014

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jul 12, 2015

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 17, 2014

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jul 12, 2015

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedAug 17, 2014

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Jul 12, 2015

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJun 25, 2013

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJun 25, 2013

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJun 25, 2013

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJan 4, 2011

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJan 4, 2011

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJan 4, 2011

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJan 4, 2011

PVT: RESOLVED BY SATISFACTORY CAT 1 INSPECTION · disposed Apr 5, 2015

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedMar 14, 2010

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedMar 14, 2010

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedMar 14, 2010

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedOct 12, 2009

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedOct 12, 2009

PVT: RESOLVED BY SATISFACTORY CAT 1 INSPECTION · disposed Apr 5, 2015

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedOct 12, 2009

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedOct 12, 2009

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJul 10, 2008

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

E-ELEVATOR ELEVATORREQUIRED — V*-DOB VIOLATION - ResolvedJul 10, 2008

PVT: SATISFIED BY SUBMISSION OF AOC FOR CAT 1 INSP · disposed Apr 1, 2014

DOB BIS Violations (3h2n-5cm9), NYC Open Data. As of October 27, 2026.

ECB violations

Environmental Control Board · NYC Open Data

Unknown — CLASS - 2ACTIVE · Jun 19, 2017

FAILURE TO FILE ANNUAL CERTIFICATION THAT COOLING TOWER 1000020371 HASBEEN INSPECTED, TESTED, AND DISINFECTED, AND THAT A MAINTENANCE PLAN HAS BEEN DEVELOPED AND IMPLEMENTED BY NOVEMBER 1, 2016.RMDY: FILE ANNU

Penalty: $2,000 · paid: $2,017

24 resolved, most recent Jun 19, 2017
Unknown — CLASS - 2RESOLVE · Jun 19, 2017

FAILURE TO FILE ANNUAL CERTIFICATION THAT COOLING TOWER 1000002895 HASBEEN INSPECTED, TESTED, AND DISINFECTED AND THAT A MAINTENANCE PLAN HAS BEEN DEVELOPED AND IMPLEMENTED BY NOVEMBER 1,2016.REM:FILE ANNUAL CE

Construction — CLASS - 2RESOLVE · Dec 9, 2013

WORK DOES NOT CONFORM TO APPROVED AND/OR APPROVED AMENDMENTS. NOTED: 42 STY ALT TO FACADE W/PERMIT #121720496 HAS SITE SAFETY PLAN FILED W/PROTECTION NOT AS PER PLAN. APPROVED PLAN SHOWS ROOF TOP AT EXP 4 OF

Unknown — CLASS - 2RESOLVE · Dec 9, 2013

SEC. BC 3301.7. DESIGN DRAWING REQUIRED BY THE PROVISION OF CHAPTER 33. NOTED: AT FACADE ALT #121720496 HAS ERECTED STAIR SCAFFOLD TO APPROX12FLR SETBACK ON TOP OF SIDEWALK SHED W/NO DESIGN PLAN.SHED PLAN CALLS

Unknown — CLASS - 2RESOLVE · Dec 9, 2013

SEC. BC 3310.6. DESIGNATED SITE SAFETY MANAGER. NOTED: AT 42 STY FACADE JOB #121720496 FOR SITE SAFETY, WILLIAM BELLINI #MOO1413 IS DESIGNATED SS MANAGER ON PW-2. WHEREAS LOG BOOK STATES LAST SS MANAGER

Penalty: $400 · paid: $400

Unknown — CLASS - 1RESOLVE · Dec 9, 2013

BC3310.8.3 FAILURE TO COMPLY RULES PROMULGATED BY THE COMMISSIONER-SITE SAFETY RULES.NOTED: AT 42 STORY FACADE ALTERATION #121720496 HAS SITE SAFETY LOG BOOK OUT OF DATE. LAST ENTRY WAS NOV 18,2013 WITH RIGGER

Penalty: $400 · paid: $400

Local Law — Non-HazardousRESOLVE · Jun 24, 2004

FAILURE TO SUBMIT A FIFTH ROUND TECHNICAL REPORT: PERIODIC INSPECTION OF EXTERIOR WALLS AND APPURTENANCES AS REQUIRED BY LOCAL LAW 11 OF 1998 AND THE DEPARTMENT OF BUILDINGS RULES AND REGULATIONS. REMEDY: FILE

Penalty: $2,500

Elevators — Non-HazardousRESOLVE · Mar 10, 2002

73U07/14M07/ 73/U-PROVIDE CITY ID TAGS AS PER CODE 14/M-PROVIDE CERTIFICATE FRAME AS PER CODE

Penalty: $350 · paid: $350

Plumbing — Non-HazardousRESOLVE · Jun 6, 2000

USE OR INSTALATION OF PLUMBING MATERIALS ON EQUIPMENT WHICH DOES NOT COMPLY WITH R.S 16- REMEDY: REMOVE NON- COMPLYING MATERIAL OR EQUIPMENT .PVC FROM DRIP PAN TO A RISER WHICH IS TOO SAMLL FOR A BUILDING 42 ST

Plumbing — Non-HazardousRESOLVE · Dec 5, 1999

PLUMBING WORK WITHOUT A PERMIT . REMEDY : OBTAIN A PERMIT IF FEASIBLE OR RESTORE TO PRIOR LEGAL CONDITION. IN DIRECT COMING OFF THE AIR CON-DITIONER UNITS TO BE ISTALLED BY A LICENSE PLUMBER

Site Safety — HazardousRESOLVE · Aug 25, 1999

FAILURE TO SAFEGUARD PUBLIC AND PROPERTY EFFECTIVE BY CONSTRUCTION OPERATIONS IN THAT CONSTRUCTION MATRIALS FELL FROM THE BLDGS AND STRUCK A POLICE CAR & A TAXIS CAB, BREAKING THE WIND SHEILDS ON AUG,25,1999.

Penalty: $1,500 · paid: $1,500

Site Safety — HazardousRESOLVE · Jan 4, 1999

ESCAPE HATCH NOT AS PER CODE AT TIME OF INSPECTION THE METAL SHEAL OS CPMSTRUCTED OF METAL AND 2X4 ;UMBER IT DOES NOT HAAVE TWO LADDERS OR A METAL OR PLYWOOD SMOKE BARRIER ON OTHER FLOOR 19 FLOOR IS BEING POURE

Penalty: $2,500 · paid: $2,500

Construction — Non-HazardousRESOLVE · Sep 15, 1998

WORK W/O PERMIT. AT TIME OF INSPECTION NEW PLUMBING WORK WAS OCCURRINGCONSIST OF NO HUBB CAST IRON PIPE 4"X6" DRAINAGE. DEPT RECORD SHOW NOPERMIT WAS ISSUED FOR SAID WORK. REMEDY: OBTAIN PERMIT FOR SAID WORK.

Construction — Non-HazardousRESOLVE · Mar 4, 1998

WORK WITHOUT A PERMIT. NOTED: PAD INSTALLED FOR PERSONELL HOIST. A REVIEW OF BLDG DEPT RECORDS INDICATE THAT NO PERMIT WAS ISSUED. REMEDY: OBTAIN PERMIT.

Construction — Non-HazardousRESOLVE · Mar 4, 1998

WORK WITHOUT A PERMIT. IN THAT NO PERMIT WAS ISSUED FOR THE ERECTION OF A PERSONELL HOIST. REMEDY: OBTAIN PERMIT.

Site Safety — HazardousRESOLVE · Feb 23, 1998

FAILURE TO SAFEGUARD PUBLIC DURING DEMOLITION OPERATIONS. NOTED NO GUARDRAIL PROVIDED AROUND DEBRIS CHUTES AT BASEMENT LEVEL AFTER BEING TOLD 3 TIMES TO PROVIDE A GUARDRAIL. DEBRIS BEING DUMPED FROM 7TH FLOOR

Penalty: $1,500 · paid: $1,500

Construction — Non-HazardousRESOLVE · Feb 23, 1998

WORK WITHOUT A PERMIT:-NOTED REMOVED GLASS FROM EXTERIOR WINDOW ON 2ND 3RD 4TH 5TH 6TH 7TH AND 8TH FLOORS WITHOUT A DEMOLITION PERMIT. STOP ALL DEMOLITION WORK REMEDY:-OBTAIN NECESSARY PERMIT.

Penalty: $500 · paid: $500

Site Safety — HazardousRESOLVE · Feb 23, 1998

FAILURE TO SOLIDLY BOARD UP WINDOWS ON THE SEVENTH FLOOR WHILE DEMOLITION OPERATIONS AREA IN PROGRESS AFTER BEING WARNED 2 TIMES PREVIOUSLY. REMEDY: STOP ALL DEMOLITION WORK UNTIL ALL WINDOWS ARE BOARDED UP.

Penalty: $500 · paid: $500

Construction — Non-HazardousRESOLVE · Feb 1, 1998

WORK WITHOUT A PERMIT. NOTED: A SECTION OF WALL ON NORTH SIDE DEMOLISHED FOR REMOVAL OF DEBRIS W/ A BOB CAT FROM BLDG TO A CONTAINERON STREET. A REVIEW OF BLDG DEPT RECORDS INDICATE THAT NO PERMIT WAS

Construction — Non-HazardousRESOLVE · Jan 25, 1998

WORK WITHOUT A PERMIT. NOTED: PLUMBING FIXTURES REMOVED FROM RESTROOMSREVIEW OF BLDG DEPT RECORDS INDICATE THAT NO PLUMBING PERMIT WAS ISSUED. REMEDY: OBTAIN NECESSARY PERMIT.

Site Safety — HazardousRESOLVE · Jan 25, 1998

DEMOLITION IN AN UNSAFE & PROPER MANNER. NOTED: EGRESS DOORS LEADING OUT TO PARK AV CHAINED & PADLOCKED. STOP ALL WORK. REMEDY: PROVIDE AMEANS OF EGRESS AT ALL TIMES.

Site Safety — HazardousRESOLVE · Jan 25, 1998

FAILURE TO REMOVE ALL GLASS IN INTERIOR PARTITIONS AND PUT PLYWOOD AGAINST WINDOWS IN THE EXTERIOR WALLS PRIOR TO THE COMMENCEMENT OF DEMOLITION OPERATIONS. NOTED DEMOLITION IN PROGRESS IN THE BASEMENT AND ON

Site Safety — HazardousRESOLVE · Jan 25, 1998

FAILURE TO SAFEGUARD PUBLIC IN THAT NO LIGHTING WAS PROVIDED ON 2 STAIRS AT DIFFERENT LOCATIONS. FROM 1ST TO 2ND FL & ELEVATOR LOBBIES ON 2ND-3RD & 4TH FLS. STOP ALL DEMOLITION WORK.

Site Safety — HazardousRESOLVE · Jan 25, 1998

FAILURE TO SAFEGUARD. NOTED: ELEVATOR DOORS ON 2ND-3RD & 4TH FL OPEN LEAVING ELEVATOR SHAFT OPEN DOWN TO BSMT. NO BARRICADE WAS PROVIDED IN FRONT OF OPENINGS & THE LOBBIES VERY POORLY LIGHTED. STOP ORDER.

Construction — Non-HazardousRESOLVE · Sep 17, 1989

INSTALLED NEW WATER TANK AT ROOF WITH NEW OAK DUNNAGE BEAMS AND GALVANIZED HOOPS FLAT AND CONICAL COVERS WITH 2 1/2 YELLOW CEDAR WOOD WITHOUT FIRST OBTAINING A PERMIT. REMEDY FILE WITH THIS DEPT OBTAIN APPROVAL

Penalty: $125 · paid: $125

ECB Violations (6bgk-3dad), NYC Open Data. As of October 27, 2026.

What are you trying to do here?

Public records for 515 PARK AVENUE, Manhattan. Data from NYC Open Data: NYC MapPLUTO, Department of Buildings (DOB NOW, BIS, ECB), Housing Preservation and Development, Landmarks Preservation Commission, ACRIS (NYC Department of Finance), DOF Digital Tax Map. Address lookup by NYC Planning Labs Geosearch. Page updated October 27, 2026.